Welcome to a sample of DevProMM
Welcome to a sample of DevProMM
This Sample of DevProMM (Development Project Management Method)has been provided to give you a feel for the layers and content of the full version. Only a small amount of the total content of DevProMM is visible in this sample. some layered content has been included, which is indicated by the "live" activity boxes. Greyed-out activity boxes do not work in this sample. | ||
The term "Project Management Method" (PMM) means that it:
|
The Method uses standard project management processes and procedures to deliver affordable housing developments & regeneration schemes. It is consistent with: |
|
HCA scheme audit requirements | GLA scheme audit requirements | Clients' Commitments |
ISO 21500:2012 (Guidance on Project Management) | BS 6079 (Project Management) | PRINCE2 |
Association for Project Management's Body of Knowledge v6 | RIBA Plan of Work 2013 | BSRIA Soft Landings 2018 |
Want to Comment on Pages?
If you want to leave a Comment on any of the pages, you need to be logged in. If you are not logged in, look at the top-right of the page for the "Login" button!
DEFINITIONS
A land-led scheme is one where we are purchasing land independently, and can choose who will be our consultants and building contractor. We have complete control over the design and standards of the finished products (within our financial and time constraints, of course) |
Package Deal is a term that covers a range of scenarios, the common features of which are the land is brought to us by a housebuilder or builder, partly designed, and we enter into a negotiated building contract with them for the construction. Therefore, unlike land-led schemes, we do not have control over who will build it. Regarding what to be built, the term covers a spectrum of control, and could be simplistically subdivided as follows: Early-Involvement Package Deal: we are involved very early in the design process (no design, or simple proving layouts having been completed). We then provide the house builder/builder with our Design Brief, and work with their design team to develop designs that meet our requirements, for which we then seek a planning permission. We provide the house builder/builder with our Employers Requirements, negotiate a contract sum and enter into the building contract. Very akin to land-led schemes, where we control what is built, although we do not control who builds it. Late-Involvement Package Deal: we are involved when RIBA Stage 3 designs have been completed (maybe before a planning application or after permission is granted), and therefore have very little control over design. We provide the house builder/builder with our Employers Requirements (influencing or controlling the materials, systems and components to be used), negotiate a contract sum and enter into the building contract. Package Deal As Off - Plan Purchase: if we are involved when a full planning permission has been granted for the housebuilder’s standard dwelling types, and there is therefore very little or no opportunity to influence either the design or the material systems and components, we are essentially being offered a finished product. Whatever it is called, this is really an Off-Plan Purchase, even if the purchase mechanisms involve a contract to buy the land and a construction contract. |
An off-plan purchase (OP) is where we are offered some fully-designed and specified dwellings with no - or very little - choice over design or components. Essentially a finished product, there may be some choices over kitchen and bathroom fittings and some finishes such as paint colour. Not only do OP purchases offer little or no control over the design / specification, they usually aren't available for occupation for several months (i.e. while they are being built). |
An off the shelf (OTS) purchase is when the Association buys some completed dwellings that are ready to let / sell. These may be new builds that have just completed, a refurbishment or rehabilitation of older buildings into new dwellings, or the purchase of second-hand street property. OTS purchases offer no control over the design / specification, but they are available for occupation very quickly. |
Section 106 schemes can:
Private Rented Sector schemes are all:
|